Next iteration for threefold.io website #197

Closed
opened 2024-06-21 09:22:58 +00:00 by Amanda · 5 comments
Member

The following can be completed in the upcoming sprint (24th Jun to 7th Jul)

https://github.com/orgs/threefoldfoundation/projects/97/views/1

The following can be completed in the upcoming sprint (24th Jun to 7th Jul) https://github.com/orgs/threefoldfoundation/projects/97/views/1
Amanda added this to the June 24 – July 07 project 2024-06-21 09:22:58 +00:00
Owner

We have been spending a lot of time on the tagging issue for the past days. Updates directly in the issues.

We have been spending a lot of time on the tagging issue for the past days. Updates directly in the issues.
Owner

Progress can be tracked at the project level. Will be complete this week.

Progress can be tracked at the project level. Will be complete this week.
gosam self-assigned this 2024-07-04 12:01:13 +00:00
Amanda was assigned by gosam 2024-07-04 12:01:13 +00:00
gosam modified the project from June 24 – July 07 to July 08 – July 21 2024-07-08 10:01:15 +00:00
Owner

Nearly done here, just two issues remaining. Need to sync with Timur but he was quite busy today. Will check in again tomorrow.

Nearly done here, just two issues remaining. Need to sync with Timur but he was quite busy today. Will check in again tomorrow.
Owner

I coordinated with Timur today on the last two issues. Should be completed by tomorrow.

I coordinated with Timur today on the last two issues. Should be completed by tomorrow.
Owner
https://github.com/threefoldfoundation/www_threefold_io/pull/429
gosam closed this issue 2024-07-10 12:26:23 +00:00
Sign in to join this conversation.
No Milestone
No Assignees
2 Participants
Notifications
Due Date
The due date is invalid or out of range. Please use the format 'yyyy-mm-dd'.

No due date set.

Dependencies

No dependencies set.

Reference: tfgrid/circle_promotion#197
No description provided.