# Grid Release Timeline
|
||
|
|
||
|
## Introduction
|
||
|
|
||
|
Each grid release follows a clearly defined timeline. This ensures all the tasks are done properly.
|
||
|
|
||
|
## Template
|
||
|
|
||
|
Each grid release should have in its project kanban one issue containing the template below, adjusted with the current grid release.
|
||
|
|
||
|
```
|
||
|
# X.YZ Grid Release Timeline
|
||
|
|
||
|
We provide the overall guideline for X.YZ grid release. Making sure all those steps are done in order will ensure the grid release is done efficiently.
|
||
|
|
||
|
- [ ] Stakeholders meet and define the grid release specs
|
||
|
- [ ] Specs are turned into stories in a grid release project kanban
|
||
|
- [ ] Stakeholders confirm the stories as fulfilling the specs and grid release goals (with Grid+stories ETA)
|
||
|
- Make sure not to add stories in the middle of the sprint
|
||
|
- If there is a need, it needs to be agreed upon
|
||
|
- [ ] Comms circles write a forum post explaining the specs of the grid release, preparing community members to the grid release GEP
|
||
|
- [ ] Stories are worked on and completed
|
||
|
- When a grid release project is completed (all stories are completed)
|
||
|
- [ ] Stakeholders meet and review the stories, confirming they are correctly done
|
||
|
- [ ] A post summarizing the GEP is posted on the forum, written by Ops (Sabrina)
|
||
|
- [ ] When the GEP is passed, devs and ops implement the new features of the grid (e.g. publish to all networks)
|
||
|
- [ ] Comms circle communicate with the community that the grid release is done
|
||
|
|
||
|
```
|
||
|
|
||
|
For an example, see the 3.16 version [here](https://git.ourworld.tf/tfgrid/circle_engineering/issues/126).
|